Bathroom Renovation Timeline
We are a home renovation contractor ready to renovate your bathroom.
Timeline Description
WE RENOVATE BATHROOMS IN LADNER, TSAWWASSEN, DELTA, AND THE GREATER VANCOUVER AREA
Day 1-2
- Site preparation
- Floor protection
- Dust barrier protection
- Demolition of bathroom finishes/flooring/cabinets/drywall
- Layout/framing/backing for new floor plan
- New subfloor if necessary
Day 3
- Rough-in plumbing
- Installation of tub
Day 4
- Rough-in electrical
- Install exhaust fan with venting
Day 5-10
- Drywall necessary areas
- Apply Redgaurd and moisture resistant board
for tub surround area and for tile application
Note: A few days may be added to drywall process if:
– Extensive drywall work is needed
– Room temperature does not allow mud to dry quickly
– Ceilings are being changed from a textured to a smooth profile
Day 10-14
- Installation of tile for floor and walls
- Grouting and sealing of tiles
Day 14-15
- Prime and paint walls. First coat
Day 15-16
- Install vanity and counter top
- Finish carpentry
Note: If the counter top needs to be custom measured, it may take 7-10 business days before
installation
Day 17
- Install finish plumbing fixtures
Day 18
- Install finish electrical fixtures
Day 19-21
- Install accessories towel bars, robe hooks, paper holders etc.
- Final paint touch ups
- Detailed clean
Note: – This is only example. Do not assume that all bathrooms will fall into this timeline. Smaller simple re and re renovations will be completed faster where as large renovations with extensive structural work may take longer. Various obstacles may interrupt the foreseen schedule and cause delays. New Vision Projects Inc. will do their
best to complete your project in the least amount of time without compromising the quality of our
workmanship.
A few things that may affect your schedule:
- Unexpected concealed items such as rot or water damage exposed during demolition
- Special order items that will have to be delivered
- Products that arrive damaged and must be returned
- Fixing existing items that may not have been installed correctly in the first place
- Shower glass doors and stone counter tops that have to be measured for on site
- Weather conditions
Home Building & Renovation Planning
GET YOUR RENOVATION OFF TO A GOOD START AND ENSURE THE BEST RESULTS
Carefully Plan Your Project
Some renovations and additions, such as converting a bungalow to a two-story home, will require that you move out during construction. Other projects, such as an addition above an attached garage or a refurbished kitchen, may allow you to live with the building project – but there will be inconvenience and disruption that you’ll have to plan for.
Major projects may require the services of an architect and other professionals such as engineers and heating contractors. Their drawings are not only required to obtain building permits and other municipal approvals, but they provide the basis for your renovation contractor to price the project.
Be realistic about the time a project will take to get started and to complete; its full costs, including at least a 10 per cent contingency for changes and unexpected conditions; and the impact the project will have on the daily operation of your home and family activities.
If your project is likely to last more than a few weeks, it’s wise to discuss your project with neighbours. In addition to unavoidable noise and dirt, there will be vehicles parked on the street, disposal bins in the driveway, and plenty of truck deliveries. Most neighbours will be understanding and accommodating, especially if notified first.
Include a requirement for daily clean-up in your contract, so that your home, your street and nearby lawns don’t end up resembling a construction site.
Select a RenoMark Renovator/Builder
Look for a RENOMARK renovator as your assurance that you have hired a professional who will provide high quality services.
Ask about the renovator’s experience with projects similar to yours. We recommend that you get the names of homeowners who have had equivalent work done and ask them about their experience.
It’s wise to contact a renovator first. Many RENOMARK renovators have in-house design professionals or relationships with architects and others who specialize in designing residential renovation projects. If you engage a designer first, bring a renovator into the team as early as possible so that the experience and expertise of each party can benefit your project.
At this stage your design professional or your renovator should be able to provide rough sketches satisfactory to give you confidence to proceed or to refine your plans. A preliminary sketch and a general indication of the quality of materials and workmanship you seek (the “specifications”) will allow the renovator to give you a budget estimate and an indication of the time it will take to finalize design, obtain building permits or other approvals, and complete the project.
Your RENOMARK renovator will select and manage experienced trades people for specific elements, such as electricians, plumbers, painters, or those who apply drywall, brick or stucco.
Get a Written Contract
Once you are satisfied with a preliminary design, a preliminary budget and a realistic timetable, you are ready to commit to final drawings. When these are complete you are in a position to get an accurate estimate of the cost and to sign a contract with a renovator to perform the work.
If you decide to ask more than one renovator to submit bids, remember that this can be a time-consuming effort. The renovator has to be very precise in pricing materials according to the specifications… because he will be locked in to the price.
When you make your decision to hire a renovator, get it in writing. Include the precise scope of work; the exact price, including a schedule of payments; a reasonable timetable for completing the work; and any instructions for protecting parts of the house not under construction.
If there is any difference of opinion between your renovator and your design professional about procedures or materials, this is the time to resolve it. It is important to avoid any significant changes during construction because this may cause delays and extra cost.
Avoid renovators who offer to do work without a contract in an attempt to avoid payment of the HST. This type of renovator may also not be paying WorkSafeBC or carrying adequate insurance, leaving you at financial risk.
Check of the Progress
Regular communication between you and your renovator may avoid problems. During the course of a renovation or addition it is common for the homeowner to request changes or ask for additional work. These requests may affect the cost and time it takes to complete your project. It is important that you have a signed change order for all changes. Make sure that you are aware of additional costs and that these changes are added to the contract. Better still, try to think of these things during the planning stage – you don’t want to be ordering additional flowers on the wedding day!
Discuss Your Concerns
Raise any concerns you may have without delay. Schedule meetings with your renovator when he or she can address your concerns without distraction.
Your renovator will discuss any concerns that you may have with the project or items that do not meet your expectations. But be flexible when minor changes occur that do not affect either the appearance or function of the job. Note any changes that are made as a result of such conferences, and do so in writing.
Follow Us To See What We've Been Doing
Catch up with us on social media and our blog, including Instagram, Facebook, and Houzz

New Project Manager Position Opening
Are you a self-driven, organized, team oriented, project manager that loves residential/commercial construction? Do you thrive in a fast paced, ever changing work environment and have a track record of getting results through planning and execution? Would you like to...